Members of the group Keep Reno Heavenly showed a mix of emotions after the Reno County Commission denied NextEra Energy a permit to build a wind farm in the southeastern part of the county.

On one hand, all of its efforts had paid off. Members of the group had worked for months to organize and participate in public hearings, and they finally got the result they wanted — the proposed 220 megawatt wind farm with more than 80 turbines reaching 500 feet in the air would not be built.

Brian Grimmett

Standing near the corner of his property in southeastern Reno County, Nick Egli looked east and pointed to the proposed locations for several 500-feet-tall wind turbines.

Egli is standing on a grass airstrip he’s spent the last 10 years building. He pictures a few more homes, some hangars and, eventually, a residential community for pilots of small planes.

“If there’s turbines there, you’ve completely killed everything I’ve been working on the last 10 years,” he said.

A Florida-based developer is exploring the possibility of building a wind farm in Douglas County.

NextEra Energy Resources is looking for sites to place meteorological towers to measure the wind in the area. Company spokesman Steve Stengel says the measurements will determine if a Douglas County project would be economically feasible.

He says the company also wants to find out if there are enough landowners willing to sell easements on their land for wind turbines to make a project possible.